Current projects and requests:
- 2024 Road & Utility Improvements will consist of water main and street reconstruction on Orchard Ave from Lake to the alley and the west section of the alley from Orchard to Park Ave and the water main relay and street construction on Park Hill Drive from Lakeview Ct to Oaklawn Ct.
Orchard Avenue & Park Hill Drive Updates:
- 11/1/24 Update:
Paving will begin November 2, 2024, paving on Park Hill and Orchard Ct. Please do not park on the new pavement.
- 9/13/24 Update:
The Pewaukee Road and Utility Improvements Project started this week with water main work on Park Ave. and continuing down Orchard Ave Alley. Your patience and understanding is appreciated with the partial closure on Park Ave. It will be paved and reopen before the weekend.
Orchard Ave.
Week of 9/23 – Water Main installation will be tested this week. Residents may experience slight delays, please be patient as the contractor will get traffic through.
Park Hill Dr. (Oaklawn Ct. to Lakeview Ct.)
Week of 9/23 –Water main installation will continue. Please be patient in single-lane traffic work zones.
*Schedule is weather dependent. No parking on roadways in work areas.
- 10/01/24 Update:
Orchard Ave.
Week of 10/01 - Water service installations to occur this week. DPW workers will knock on doors to notify residents when water service connections will be made. Homeowners will be without use of water for approximately one hour and notified when back on.
Park Hill Dr. (Oaklawn Ct. to Lakeview Ct.)
Week of 10/01 - Water main installation has finished. Main will be tested this week.
- 10/21/24 Update:
Orchard Ave.
Installation of concrete curb and gutter, sidewalks, handicap ramps and driveway aprons. There will be limited to no access to driveways so please check your doors and mailboxes for notices and durations.
Park Hill Dr.
Water main connections will be installed with daily shut downs, please check doors for notices. Water main services will also be installed, homeowners will be notified of shutdown during connection. Installation of concrete curb and gutter, sidewalks and handicap ramps.
There will be a lot of activity this week so please be patient and use alternate routes if feasible.
Anticipated Construction Projects:
2023
- Mill and re-pave of Concord Road and Meadow Creek Court
- Pulverize and pave of Hickory Street east of Forest Grove
- Removal and repaving of the alley between Hickory and Oakton
- 1010 Quinlan water reservoir rehabilitation
- Kopmier Drive sanitary lift station replacement
- Repaving of Savoy Ct
2022
- Stone Ct, Briar Ct, Timber Ridge, and Lexington Ct - mill and overlay
- East Wisconsin Ave - street and utility reconstruction (Due to start August 1st)
2021
Replace water main relay on Evergreen Lane
- Replace the 1950's cast iron water main with a modern 6" pipe
Park Hills Sanitary Relay
- Sanitary sewer project will be in the easement located east of the Cheshire and High Street intersection
- Replace the existing 8" pipe with a 12" pipe to accommodate existing and future wastewater flows
- Replacing 1,152 feet